[ARCHIVED] Bridge Street Repair Project

Bridge Street

Repairs and improvements are scheduled to be done on Bridge Street starting Tuesday, October 14th.

Repairs to Bridge Street between Blackburn Street and Beck Street are scheduled to begin Tuesday, October 14th. 

The work will consist of reconstruction of some areas, as well as the repair of others. Additional new improvements will also include:

  • ADA-compliant curb ramps
  • Green bike lanes
  • Thermoplastic striping
  • Speed Tables

Schedule

Work will begin Tuesday, October 14th and last through December 8th, weather permitting. Construction crews will be active Monday through Friday, 7AM-6PM, excluding Holidays. When the crew works on the CalTrans Right of Way, construction will be done between the hours of 9:00AM and 3:00PM. 

Funding

This project will cost $919,883.50 and will be partially funded by Measures R and D. 